Lobby Renovation

The Lobby Renovation project is well underway and we expect
construction to start in the coming months:

  • Architect Secured: Steven Kratchman
  • We have received updated bids from 5 contracters and will be moving onto the interview phase of the process in the coming weeks
  • Revised bids were requested to ensure we stay on budget
  • Based on the American Institute of Architects (AIA) process, we estimate that construction may be able to begin as early as May but will continue to keep shareholders apprised of any updates.
  • Floorplan and Mood Board of materials in PDF above
  • Details of steps completed to date:
    • By Nov 18 2021- Retain Consultants, forward backgrounds and details (COMPLETE)
    • By Dec 15 2021- Complete CD and coordinate with consultants Complete CD/Bid/Filing set (COMPLETE)
    • December 2021/Jan 2022- Issue for Bid, Bid RFI’s, bid field visits, bid leveling, (COMPLETE)
    • February 2022- Issue for filing with DOB, DOB approval, Award Contract, Negotiations, Pull permits, Start Construction (IN PROGRESS)