June 2022
LOBBY RENOVATION
The Lobby Renovation project is well underway and we expect
construction to start very soon:
- Architect Secured: Steven Kratchman
- NEW! Contractor Chosen: Legacy
- Details of steps completed to date:
- By Nov 18 2021- Retain Consultants, forward backgrounds and details (COMPLETE)
- By Dec 15 2021- Complete CD and coordinate with consultants Complete CD/Bid/Filing set (COMPLETE)
- December 2021/Jan 2022- Issue for Bid, Bid RFI’s, bid field visits, bid leveling, (COMPLETE)
- February-March 2022- Issue for filing with DOB, DOB approval, Award Contract, Negotiations, (COMPLETE)
- Pull permits (COMPLETE)
- Next steps: Start Construction (IN PROGRESS)
COMMERCIAL SPACE UPDATE
The board has just signed an exclusive broker contract with Douglas Elliman to show the commercial space, which will be the fourth broker actively showing the space. Douglas Elliman knows our building and the neighborhood very well and their extensive contacts and deep knowledge of the commercial market should attract more potential businesses to view and ultimately lease the space. While businesses have expressed interest in the space it’s a